ACI 308 Curing Guide, Summarized
ACI 308 is the American Concrete Institute's curing family. The guide, now ACI PRC-308-26 (May 2026), explains methods and why curing matters, but it may not be cited in contracts. The enforceable part is ACI SPEC-308.1-23, a reference spec for external curing of cast-in-place concrete that you name in the project spec.
When a spec says “cure per ACI 308,” it can mean two documents, and one of them is not allowed in a contract. This page sorts out which is which, what changed in 2023 and 2026, and which numbers you can quote. The full ACI texts are paid; everything here comes from ACI’s free previews and FHWA’s summary, each linked.
What is ACI 308?
ACI 308 is the curing work of ACI Committee 308. It produces two documents: a guide that explains curing and a specification you can cite. The guide is now ACI PRC-308-26, Curing of Concrete Guide, 44 pages, published in 2026.
| Document | Type | Status | What it is for |
|---|---|---|---|
| ACI PRC-308-26 | Guide | Current, published May 2026 | Methods, materials, monitoring, background |
| ACI 308R-16 | Guide | Superseded by PRC-308-26 | The 2016 edition most search results still show |
| ACI SPEC-308.1-23 | Specification | Current, published June 2023 | Mandatory curing requirements for the project spec |
| ACI 308.1-11 | Specification | Superseded by SPEC-308.1-23 | Older spec still named in many master specs |
The PRC-308-26 preview gives the history: first published as a standard in 1971, revised in 1992, turned into a guide in 2001, and revised in 2016. If your spec still says 308R-16 or 308.1-11, ask whether the newer edition is acceptable.
What is the difference between ACI 308 and ACI 308.1?
The guide explains; the spec requires. PRC-308-26 states that “Reference to this document shall not be made in contract documents” and that curing measures, in general, are specified in ACI SPEC-308.1. So the guide is for learning and planning, and 308.1 is what goes in the spec book.
The SPEC-308.1-23 preview calls it a reference specification, titled External Curing of Cast-in-Place Concrete. It was approved in March 2023, published in June 2023, and supersedes 308.1-11. The project spec cites it and fills in the choices it leaves to the designer.
One trap: the 308.1-23 preview says not to use it alongside ACI 301 or ACI 350.5 unless the contract documents state that 308.1 governs. ACI 301 carries its own curing rules, and two sets of rules on one slab invite a dispute.
What does the ACI 308 curing guide cover?
The 2026 guide covers why concrete needs curing, the methods and materials, curing for different kinds of work, and how to check that curing worked. Per its contents page, the main chapters are:
- Understanding curing: hydration, the curing-affected zone, properties curing changes, elevated temperatures, sustainability
- Methods and materials: water curing, initial curing, final curing, termination, cold and hot weather, accelerated curing, minimum requirements, temperature limits
- Types of construction: pavements and slabs on ground, buildings and bridges, mass concrete, colored floors and slabs
- Monitoring: site conditions, verifying the curing went on, maturity method, assessing effectiveness
The scope note lists topics added or expanded in this edition: internal curing, curing at elevated temperatures, sustainability, curing of moisture-sensitive flooring, sensors for mass concrete, and new monitoring methods.
It also flags low-carbon cements. The guide says Type IL cements are in current use, their curing needs are being studied, and “Early indications are that initial and intermediate curing are critical to the concrete performance.” If you pour a lot of Type IL mixes, do not skip the early steps.
What are initial, intermediate and final curing?
ACI splits curing into stages by what happens on the slab. The stage definitions are from the PRC-308-26 preview. The measures column draws on FHWA’s summary of 308.1-98 and Dayton’s curing guide.
| Stage | When | Typical measures |
|---|---|---|
| Initial curing | Placement to final finishing | Fogging, evaporation retarder |
| Intermediate curing | After finishing, before final curing is in place | Continue initial measures |
| Final curing | Final finishing to end of curing | Water, sheeting, curing compound |
The point of the split is timing. A curing compound is a final curing measure, so it goes on after finishing, not during it. For how each method compares on the job, see our concrete curing methods guide.
The guide defines curing as keeping moisture and temperature conditions right so the cement can hydrate and the mix can develop its potential properties. Its objectives are to prevent moisture loss and keep a favorable temperature for long enough.
How long does ACI require concrete to be cured?
The current duration clauses sit in the paid SPEC-308.1-23 text and are not in the free preview. The best public numbers are from older editions, as summarized by FHWA’s guide for curing concrete pavements. Treat them as history and check the current edition.
| Document (per FHWA) | Duration |
|---|---|
| ACI 308.1-98 | 7 days default when above 10°C (50°F); may end early at 70% of specified strength |
| ACI 308-92 | 3 days Type III cement, 7 days Type I, 14 days Type II |
| ACI 308-92, pavements | 7 days or until 70% of specified strength |
| ACI 301-96 | 7 days; 3 days for high early strength concrete |
The 7 day figure appears in each of these documents for ordinary cement, which is why it is the number crews remember. For how cure time changes with weather and mix, see how long concrete takes to cure.
When does ACI call for a curing compound?
ACI does not require a compound over other methods. Dayton Superior’s Guide to Curing says the ACI 308 guide addresses water, plastic film, reinforced paper and liquid membrane-forming compounds. Dayton adds that wet methods work only if the concrete is kept constantly damp for 7 days.
FHWA’s summary pulls out the older ACI points that touch compounds:
- Application rate: ACI 308-92 recommended 0.20 to 0.25 L/m², about 165 to 205 ft²/gal (4.0 to 5.0 m²/L).
- Timing: ACI 301-96 says apply after the water sheen has disappeared; 308-92 warns against applying while bleeding is still going on.
- Hot weather: ACI 305R recommends a white pigmented compound to reflect sunlight.
- Low water ratio: ACI 305R calls for water curing rather than a membrane when the w/c ratio is below 0.40.
The product itself is specified by ASTM, not ACI. A plain curing compound is tested to ASTM C309. A cure and seal is tested to ASTM C1315, and Dayton Superior’s Guide to Cure and Seals says ACI 308 recommends a C1315 Type I Class A product for colored floors and slabs.
If the slab surface is dusting or soft after curing
Look at the curing record first. The guide’s “curing-affected zone” is the top layer most influenced by surface curing, and that is the layer that dusts. Late compound, a thin film, or curing pulled early all show up there first.
The ACI 308R-16 preview cites research that exposure to 90% relative humidity or less is enough to suspend hydration, and that cement at 80% hydrated at about a tenth of the rate. A surface that dries in the first days stops gaining strength.
Questions to answer before you call it a material problem:
- When did the compound go on, compared with the water sheen disappearing?
- Was the application rate on the data sheet met across the whole slab?
- Was the curing film or wet cure left in place for the specified period?
- Was there wind, sun or low humidity during finishing with no initial curing?
For repairs and how to tell dusting from crazing and curling, see dusting, crazing and curling.
Frequently asked questions
Is ACI 308R-16 still the current curing guide?
No. ACI's store marks the 2016 guide as historical. ACI PRC-308-26, Curing of Concrete Guide, was published in May 2026 and supersedes it. The guide carried the 308R name in 2001 and 2016 and is now numbered PRC-308.
What is ACI 308.1?
ACI 308.1 is the curing specification. The current edition, ACI SPEC-308.1-23, External Curing of Cast-in-Place Concrete, was published in June 2023 and supersedes 308.1-11. It is a reference spec: the project spec cites it and makes the choices it leaves open.
Can I reference ACI 308 in contract documents?
Not the guide. The PRC-308-26 front matter says reference to it shall not be made in contract documents; anything you want from it has to be restated in mandatory language. Cite ACI SPEC-308.1 instead, which is written for that purpose.
How long does ACI 308.1 require concrete to be cured?
The 2023 duration clauses are not in the free preview. FHWA's summary of the 1998 edition gives a default of 7 days above 10°C (50°F), with early termination allowed at 70% of specified strength. Check the current text before you put a number in a spec.
Does ACI 308 require a curing compound?
No. The ACI curing documents accept several final curing methods, including water, plastic film, curing paper and liquid membrane-forming compounds. The project spec picks the method.