Curing concrete

Concrete Curing Time Chart

At 70°F (21°C), ordinary Type I concrete needs about 8 days of protection to reach 65% of its 28-day strength and about 23 days to reach 95%. At 50°F (10°C) those become 11 and 29 days. Plan on foot traffic at 24 to 48 hours, cars at 7 days and sealing at about 30 days.

Last reviewed 5 min read

These charts give the numbers in one place: how many days concrete takes to gain strength at two temperatures, how long each cement type should be cured, and when you can walk, drive and seal. For the plain-language timeline and what to do day by day, see how long concrete takes to cure.

How many days does concrete take to reach strength at each temperature?

At 70°F (21°C), Type I concrete reaches 85% of its standard 28-day strength in about 16 days. At 50°F (10°C) it takes about 21. The chart below is ACI 306R’s table of how long to protect concrete to reach each strength level, as reproduced by the Federal Highway Administration.

Concrete temperatureTarget, % of 28-day strengthType I cementType II cementType III cement
50°F (10°C)65%11 days14 days5 days
50°F (10°C)85%21 days28 days16 days
50°F (10°C)95%29 days35 days26 days
70°F (21°C)65%8 days10 daysn/a
70°F (21°C)85%16 days18 days12 days
70°F (21°C)95%23 days24 days20 days

The percentages compare against “standard-cured” 28-day strength, meaning cylinders kept moist at lab temperature. The Type III cell at 70°F and 65% is left blank because FHWA flags the printed value as an error. Type III is the high early strength cement; Type II is the moderate heat cement that gains strength more slowly.

How long should each cement type be cured?

High early strength (Type III) concrete needs about 3 days of curing, ordinary Type I needs 7, and Type II needs 14. The older ACI 308 guide (1992), as summarized by FHWA, gives those three and skips Types IV and V, pozzolans and slag. The Army Corps guide spec in the same FHWA appendix covers blended mixes.

Cement or mixACI 308 (1992)Army Corps CEGS 03301
Type III, or an accelerated mix3 days3 days
Type I, IS or IP7 days (Type I)7 days
Type II, silica fume, or 25% or less fly ash or slag14 days (Type II)14 days
More than 25% fly ash or slagNo recommendation21 days

Current spec work follows ACI 308.1: 7 days with the concrete above 50°F (10°C), or until tests show 70% of specified strength. For pavements, the FHWA appendix lists ACI’s version at 7 days above 41°F (5°C) or 70% strength.

When can you walk, drive and seal new concrete?

Walk on it at 24 to 48 hours, drive a car on it at 7 days, and seal it at about 30 days. Those are general guidance from state concrete associations for normal conditions, around 70°F, so add time in cold weather.

AgeMilestoneSource
First 2 days or soProtect from freezing until it reaches 500 psi (3.5 MPa)NRMCA CIP 27
24 to 48 hoursFoot traffic on most slabsMichigan Concrete Association
7 daysMinimum curing period endsMichigan Concrete Association
7 daysCars on a new drivewayIndiana RMCA, Virginia RMCA
About 30 daysApply a sealer, on a dry day above 50 to 55°F (10 to 13°C)Indiana RMCA, Virginia RMCA
6 monthsHeavy trucksVirginia RMCA
First winterNo deicing chemicalsVirginia RMCA

The heavy truck figure varies most between sources. Virginia’s association says at least 6 months for a residential driveway, while some contractor guides say 28 days. If a loaded truck has to cross a new slab sooner, ask your ready mix supplier what strength the mix will have by then.

How does temperature change concrete curing time?

Colder concrete gains strength more slowly, and the effect is large. NRMCA’s cold weather guide says “a drop of 20°F [10°C] in concrete temperature will approximately double the setting time.” The Michigan association adds that hydration slows sharply below 50°F (10°C) and “below 40 degrees, it can stop almost entirely.”

Concrete temperatureWhat happensSource
Hot, early ageFaster early gain, lower strength at later ages than concrete cured near 70°F (20°C)NRMCA CIP 12
About 70°F (21°C)Reference temperature for the chart aboveFHWA (ACI 306R)
Below 50°F (10°C)Hydration slows a lot; NRMCA keeps curing concrete above thisMichigan Concrete Association, NRMCA CIP 11
Below 40°F (4°C)Hydration can nearly stopMichigan Concrete Association
Below about 25°F (minus 4°C)Fresh concrete freezesNRMCA CIP 27

Hot is not better. NRMCA’s hot weather guide says concrete cured at high temperatures early “will not be as strong at later ages” as the same mix cured around 70°F (20°C). In summer, cure it wet or sealed for at least 3 days and follow the hot weather curing steps.

Does a frozen or cold slab ever catch up?

A slab that stayed cold but never froze keeps gaining strength once it warms, just later. A slab that froze while fresh is different: NRMCA says “the potential strength of frozen concrete can be reduced by more than 50%.” It also says to protect concrete from freeze and thaw cycles until it reaches 3,500 psi (24 MPa).

The NRMCA curing guide asks for placed concrete to be kept above 50°F (10°C) during curing. For blankets, heaters and the rest, see cold weather concrete curing.

If you need the slab sooner than the chart allows

If the schedule is tight, change the mix before the pour, not the curing after it. NRMCA’s cold weather guide lists high early strength Type III cement, extra cement and accelerating admixtures as ways to speed strength gain, plus keeping the concrete warm with insulating blankets or heated enclosures.

Two limits apply. Accelerators do not stop concrete from freezing. Calcium chloride, the common accelerator, is capped at 2% by weight of cement. And no shortcut replaces the curing itself: keep the slab wet or sealed through the days in the cement type table above.

For a one page printout of these numbers, use the concrete curing cheat sheet.

Frequently asked questions

What is the minimum curing time for concrete?

Seven days is the usual minimum. ACI 308.1 uses 7 days while the concrete stays above 50°F (10°C), and allows stopping sooner only when tests show 70% of the specified strength. High early strength Type III cement can be cured for 3 days; Type II and mixes heavy in fly ash or slag need 14 to 21.

How many days does concrete take to cure?

Curing (keeping it wet or sealed) runs at least 7 days. Strength keeps building after that: Type I concrete held at 70°F (21°C) takes about 16 days to reach 85% and 23 days to reach 95% of its standard 28-day strength.

Does cold weather slow concrete curing time?

Yes, a lot. NRMCA says a 20°F (10°C) drop roughly doubles setting time. At 50°F (10°C), Type I concrete needs about 21 days to reach 85% of its 28-day strength, compared with 16 days at 70°F (21°C).

How can you speed up concrete curing time?

Order high early strength (Type III) cement or an accelerating admixture, place the concrete warm and keep it warm with insulating blankets or a heated enclosure. Accelerators speed strength gain but do not stop concrete from freezing.

When can you drive on new concrete?

Two state ready mixed concrete associations, in Indiana and Virginia, both say to keep cars off a new driveway for at least 7 days. The Virginia association adds that heavy trucks should stay off for at least 6 months.